The Board of Directors for Lake McQueeney Water Control and Improvement District No. 1 (LMWCID 1 or the District) would like to provide residents an update on the work performed so far at the dam for the Lake McQueeney Spillgate Replacement and Dam Armoring Project.

Since our last update, the contractor has accomplished the following:

  • The steel pile retaining wall is in place

  • Coffer dam and trestle bridge components are being stored on-site

The trestle bridge construction is ongoing. Below, find updated pictures of the work being performed.

If residents have additional questions regarding the Lake McQueeney Spillgate Replacement and Dam Armoring Project, please use the “Contact Us” form on the District website.