There has been a lot of speculation surrounding the engineering timeline for the Lake McQueeney dam repair, and the Board of Directors for Lake McQueeney WCID 1 would like to make sure residents have accurate information regarding the project and identified milestone dates.
Please note: the below timeline is proposed and there could be some change in dates. These are meant to be approximate based on current information regarding the project.
District Initiates Project Design Phase | District Initiates Project Design Phase |
Preliminary Investigations | November 2020 |
30% Design | March 2021 |
60% Design | May 2021 |
90% Design | July 2021 |
100% Design | September 2021 |
Texas Water Development Board (TWDB) Approval of Plans and Specs | November 2021 |
Advertise for Bid | November 2021 |
Contractor Notice of Award | January 2022 |
Execute Contract | February 2022 |
TWDB Approval and Issue Notice to Proceed (NTP) | March 2022 |
Construction Duration | April 2022 - April 2024 |
Weather Delay Days | May 2024 - August 2024 |
For more information as the project milestones are reached, be sure to monitor the Lake McQueeney WCID 1 news feed on the District website, and review the meeting recordings of each meeting for project updates from the Engineering Committee.