6-12-2025 Monthly Project Update
The Board of Directors for Lake McQueeney Water Control and Improvement District No. 1 (LMWCID 1, or “the District”) would like to provide residents an update on the work performed so far at the dam for the Lake McQueeney Spillgate Replacement and Dam Armoring Project.
Schedule Status:
Substantial completion date is set for mid-November 2025
Current Work Status:
Bay 3 concrete spillway slab 3.2 & 3.3 – Completed
Bay 3 concrete spillway slab 4.1 – Completed
Bay 3 concrete spillway slab 4.2 – Completed
South Abutment Wall - Started
Bay 2 concrete foundation 2nd lift – Completed
Bay 2 concrete spillway slab 3.1 – Completed
Bay 2 concrete spillway slab 4.1 – Completed
Pier 2 - Started
McQueeney control building concrete – Ongoing
Maintenance bridge steel spans assembly - Completed
Stop log storage foundation – Ongoing (Back Retaining Wall)
North Embankment dam armoring – Ongoing
South Embankment dam armoring – Ongoing
Upcoming work:
Bay 2 concrete spillway slab 4.2
South abutment concrete lift 1
South abutment concrete lift 2
Pier 2 concrete lift 1
Control building modifications and concrete walls & roof
Set HPU
North and South embankment dam armoring earthwork and concrete placements
Steel-Fab, Inc (steel gate manufacturer)
Gate manufacturing ongoing
Targeting delivery through end of July
If residents have additional questions regarding the Lake McQueeney Spill gate Replacement and Dam Armoring Project, please use the Contact Us form to submit your inquiries.