Lake McQueeney Dam Construction Update

June 16, 2025

6-12-2025 Monthly Project Update

The Board of Directors for Lake McQueeney Water Control and Improvement District No. 1 (LMWCID 1, or “the District”) would like to provide residents an update on the work performed so far at the dam for the Lake McQueeney Spillgate Replacement and Dam Armoring Project.

Schedule Status:

Substantial completion date is set for mid-November 2025

Current Work Status:

  • Bay 3 concrete spillway slab 3.2 & 3.3 – Completed

  • Bay 3 concrete spillway slab 4.1 – Completed

  • Bay 3 concrete spillway slab 4.2 – Completed

  • South Abutment Wall - Started

  • Bay 2 concrete foundation 2nd lift – Completed

  • Bay 2 concrete spillway slab 3.1 – Completed

  • Bay 2 concrete spillway slab 4.1 – Completed

  • Pier 2 - Started

  • McQueeney control building concrete – Ongoing

  • Maintenance bridge steel spans assembly - Completed

  • Stop log storage foundation – Ongoing (Back Retaining Wall)

  • North Embankment dam armoring – Ongoing

  • South Embankment dam armoring – Ongoing

Upcoming work:

  • Bay 2 concrete spillway slab 4.2

  • South abutment concrete lift 1

  • South abutment concrete lift 2

  • Pier 2 concrete lift 1

  • Control building modifications and concrete walls & roof

  • Set HPU

  • North and South embankment dam armoring earthwork and concrete placements

Steel-Fab, Inc (steel gate manufacturer)

  • Gate manufacturing ongoing

  • Targeting delivery through end of July

If residents have additional questions regarding the Lake McQueeney Spill gate Replacement and Dam Armoring Project, please use the Contact Us form to submit your inquiries.