Lake McQueeney Dam Proposed Project Timeline

June 4, 2021

There has been a lot of speculation surrounding the engineering timeline for the Lake McQueeney dam repair, and the Board of Directors for Lake McQueeney WCID 1 would like to make sure residents have accurate information regarding the project and identified milestone dates.

Please note: the below timeline is proposed and there could be some change in dates. These are meant to be approximate based on current information regarding the project.

District Initiates Project Design Phase District Initiates Project Design Phase
Preliminary Investigations November 2020
30% Design March 2021
60% Design May 2021
90% Design July 2021
100% Design September 2021
Texas Water Development Board (TWDB) Approval of Plans and Specs November 2021
Advertise for Bid November 2021
Contractor Notice of Award January 2022
Execute Contract February 2022
TWDB Approval and Issue Notice to Proceed (NTP) March 2022
Construction Duration April 2022 - April 2024
Weather Delay Days May 2024 - August 2024

For more information as the project milestones are reached, be sure to monitor the Lake McQueeney WCID 1 news feed on the District website, and review the meeting recordings of each meeting for project updates from the Engineering Committee.