There has been a lot of speculation surrounding the engineering timeline for the Lake McQueeney dam repair, and the Board of Directors for Lake McQueeney WCID 1 would like to make sure residents have accurate information regarding the project and identified milestone dates.
Please note: the below timeline is proposed and there could be some change in dates. These are meant to be approximate based on current information regarding the project.
| District Initiates Project Design Phase | District Initiates Project Design Phase |
| Preliminary Investigations | November 2020 |
| 30% Design | March 2021 |
| 60% Design | May 2021 |
| 90% Design | July 2021 |
| 100% Design | September 2021 |
| Texas Water Development Board (TWDB) Approval of Plans and Specs | November 2021 |
| Advertise for Bid | November 2021 |
| Contractor Notice of Award | January 2022 |
| Execute Contract | February 2022 |
| TWDB Approval and Issue Notice to Proceed (NTP) | March 2022 |
| Construction Duration | April 2022 - April 2024 |
| Weather Delay Days | May 2024 - August 2024 |
For more information as the project milestones are reached, be sure to monitor the Lake McQueeney WCID 1 news feed on the District website, and review the meeting recordings of each meeting for project updates from the Engineering Committee.